Smith College Admission Academics Student Life About Smith news Offices
Ford Hall Community Information

CONSTRUCTION UPDATES

Updates will be added on at least a monthly basis. The projected completion date of Ford Hall is fall 2009.

December 22, 2008

January 6 OR January 8: From 7 a.m.-4 p.m., Belmont Avenue will be closed to vehicle traffic from Green Street to the Mendenhall Hall Center for the Performing Arts service entrance for delivery of mechanical equipment to be placed on the roof of Ford Hall, which requires the use of a small crane. Pedestrian access to Belmont Avenue from Green Street will be maintained, as will both vehicle and pedestrian access from Ahwaga Avenue.

October 31, 2008

November 6: From 7 a.m.–4 p.m., Belmont Avenue will be closed to vehicle traffic from Green Street to the Mendenhall Hall Center for the Arts service entrance for delivery of roofing materials for Ford Hall, which requires the use of a small crane. Pedestrian access to Belmont Avenue from Green Street will be maintained, as will both vehicle and pedestrian access from Ahwaga Avenue. 

October 29, 2008

November 3: Beginning at 7 a.m., Belmont Avenue will be closed to vehicle traffic from Green Street to the Mendenhall Hall Center for the Arts service entrance for delivery of windows for Ford Hall. Pedestrian access to Belmont Avenue from Green Street will be maintained, as will both vehicle and pedestrian access from Ahwaga Avenue. Belmont Avenue will be re-opened to vehicle access on November 3 as soon as the window delivery is completed.

October 23, 2008

October 27: Belmont Avenue will be closed to vehicle traffic from Green Street to the Mendenhall Hall Center for the Arts service entrance from 7 a.m.–3:30 p.m. for the installation of the curtain wall frames for the third floor terrace of Ford Hall. Pedestrian access to Belmont Avenue from Green Street will be maintained, as will both vehicle and pedestrian access from Ahwaga Avenue.

October 20, 2008

October 21: Crosswalk striping will occur on West Street from the Smith parking garage to Arnold Avenue between 7 a.m. and noon. A police officer will be on site to manage pedestrian and vehicle traffic.

September 30, 2008

Green Street Sidewalk Reconstruction

Smith College’s facilities management department is replacing the sidewalks on Green Street and relocating the parking meters in order to improve walkability and the appearance of the streetscape. Through traffic on Green Street will be maintained throughout this two-phase project.

The first phase of the project involves the sidewalk from Hubbard House to the Dickinson parking lot. Work began on September 29 with the removal of the sidewalk. The new sidewalk is being installed today, September 30, along with the parking meters. Parking in that area is expected to be available tomorrow, October 1.

The second and larger phase of the project involves the section of Green Street from the Dickinson parking lot to Sage Circle. Removal of the sidewalk and parking meters is scheduled to begin on Monday, October 6, with the new sidewalk installed and parking meters relocated by Thursday, October 9. Parking on the entire street is expected to be fully restored on Friday, October 10.

This project is unrelated to the construction of Ford Hall. It is undertaken in coordination with the City of Northampton.

September 29, 2008

Current: Belmont Avenue, from Green Street to the Mendenhall Center for the Performing Arts service entrance, will be closed occasionally to vehicle traffic during the work week (Monday through Friday from 7 a.m.–5 p.m.) through April 2009 because of deliveries to Ford Hall. Pedestrian access to Belmont Avenue from Green Street will be maintained, as will both vehicle and pedestrian access from Ahwaga Avenue.

September 17, 2008

West Street Crosswalk Striping Update: Due to a delay in the delivery of materials, the crosswalk striping on West Street from the Smith parking garage to Arnold Avenue has been postponed. Notification will be provided when the rescheduled date is determined.

September 11, 2008

September 17: Crosswalk striping will occur on West Street from the Smith parking garage to Arnold Avenue beginning at 8:30 a.m. A police officer will be on site to manage pedestrian and vehicle traffic.

September 2, 2008

Belmont Avenue Paving Update: The schedule for paving Belmont Avenue has changed. It is now scheduled for Thursday, September 11, with a rain date of Friday, September 12. Reserved parking for 21 Belmont Avenue residents will be made available in the college’s Scott parking lot behind their residence for September 10–13.

Belmont Avenue will be opened for pedestrian and vehicular traffic the week of September 15.

August 28, 2008

Current: Preparations are under way for replacing the sidewalk on the west side of Belmont Avenue and paving the road. Paving is scheduled for Monday, September 8, with a rain date of Tuesday, September 9. Reserved parking for 21 Belmont Avenue residents will be made available in the college’s Scott parking lot behind their residence on September 7, 8, 9 and 10.

Belmont Avenue will be opened for pedestrian and vehicular traffic the week of September 15.

August 7, 2008

Saturday Construction Schedule: Beginning on Saturday, August 9, and on subsequent Saturdays when necessary, there will be activity on the construction site between 9 a.m. and 3 p.m.

Current: Utility work in Arnold Avenue scheduled to begin on August 11 (and described below) has been postponed.

August 4, 2008

August 11–14: Green Street will be closed to through traffic from the west side of Dickinson parking lot to Belmont Avenue for the installation of electrical, data, and telephone services to Ford Hall. The Dickinson parking lot will be accessible at all times, and a police officer will be on site to manage traffic flow.

August 11–15: Utility work in Arnold Avenue will begin on August 11 for one week. This work requires closing the west section of the road beginning at 11 and 12 Arnold Avenue between 7 a.m. and 5 p.m. daily. Smith College temporary parking is being provided to affected residents at 11, 12, and 16 Arnold Avenue and to the Green Street Café.

July 11, 2008

July 14: The construction fence at the west end of Arnold Avenue will be repositioned to install a retaining wall. All work will occur inside the construction fence and is expected to be completed by Friday, July 25, at which time the fence will be moved back to its original location. This work will not impede access to Green Street Café parking and is not expected to disrupt parking for Arnold Avenue Residents. However, temporary parking passes for the Smith College parking garage will be given to 16 Arnold Avenue residents if it turns out they should need them.

July 8, 2008

Update: The crane that will set steel at the top of Ford Hall will be delivered on Friday, July 11, in order to be set up for the work beginning on Monday, July 14. As previously indicated, the crane will be located near Belmont Avenue, within the project fences.

July 7, 2008

July 14 –August 1: A crane will be located near Belmont Avenue, within the project fence, for use in setting steel at the top level of the building.

June 25, 2008

June 30–July 11: Excavation work for telecommunications related to Ford Hall will take place in the area of Seelye Hall and Neilson Library. The work will take place in two stages. Vehicular and pedestrian circulation will be maintained in central campus throughout the project. The Neilson Library loading dock will remain accessible. Care will be taken to minimize the impact on classes in Seelye Hall. Please use caution when passing through the area.

Stage I: Trenching will take place at the west end of Seelye Hall and at the portion of Seelye Drive that is not normally open to vehicles. By July 3, when this portion of trenching is backfilled, the road will be temporarily opened for one-way traffic from Neilson Drive to the road between College Hall and the Brown Fine Arts Center.

Stage II: The one-way road from Neilson loading dock to the Dickinson parking lot will be closed so that a trench can be excavated down that drive and into the Neilson basement. Vehicles that normally enter central campus from northern end of campus will be directed down Seelye Drive and onto Elm Street near College Hall. Pedestrian traffic will be maintained but directed around these excavations as necessary.

June 19, 2008

June 23–25: Metered parking will be unavailable on the section of Green Street extending from West Street to Belmont Avenue, in order to facilitate delivery of mechanical equipment to the Ford Hall site. Green Street will remain open to through traffic and the metered parking lower on Green Street and in the Dickinson Lot will be available. A police officer will be on site to manage traffic flow.

June 4, 2008

Current: The closure of Belmont Avenue from the Green Street entrance to the service driveway next to the Mendenhall Center for the Performing Arts will continue through September 8, 2008.

Summer Construction Schedule: From June 7 through August 29, 2008, the construction work schedule will be Monday through Friday from 7 a.m.–6 p.m. There will be activity on the construction site most Saturdays from 8 a.m.–4 p.m.

June 10 and 11: The last roof level concrete pours are scheduled and are expected to be completed by 6:30 p.m. on both days.

June 11 and 13: The remaining lower level concrete pours are scheduled and are expected to be completed by 8 p.m. on both days.

May 30, 2008

June 4 and 5: There will be two cement slab pours for Ford Hall from the Belmont Avenue side of the site. One cement pour will be to the lower level of the building and the other will be to the roof level. This work will begin at 7 a.m. and is expected to be completed by 7 p.m. As stated previously, this type of work extends past normal work hours because the nature of the material requires the work to be accomplished without interruption in a single day.

May 21, 2008

May 21 and 28: Cement slab pours to the lower level of Ford Hall will occur from the Belmont Avenue side of the site. This work will begin at 8 a.m. and conclude no later than 10:30 p.m. on each day. As stated previously, this type of work extends past normal work hours because the nature of the material requires the work to be accomplished without interruption in a single day.

Current: Asphalt curbing on Ahwaga and Belmont avenues up to the construction site is completed. The installation of granite curbs on Belmont Avenue and sidewalks on both streets is scheduled for spring 2009.

June: Installation of the chilled water line on Green Street will begin on Monday, June 2, and will be completed by the end of June. Green Street will have restricted through traffic with a police officer present to direct traffic throughout the month of June.

There are two phases to the chilled water line installation. Phase one, June 2–10, will start at the junction of College Lane and Green Street and extend past Sage Hall and up to the west end of the Mendenhall Center for the Performing Arts. Parking by the Sage Hall circle will be suspended during this time to allow for through traffic.

Phase two is scheduled for June 11–27. The installation of the chilled water line will start at the west end of the Mendenhall CPA and extend up to Ford Hall. The sidewalk from the west end of the Mendenhall CPA to Belmont Avenue will be removed during this phase and a new sidewalk will be installed upon the completion of the chilled water line installation. Metered parking on the north side of Green Street from the Dickinson parking lot up to the end of the street near the Sage Hall circle will be suspended to allow for through traffic.

May 8, 2008

May 13: There will be two cement slab pours for Ford Hall from the Belmont Avenue side of the site. One cement pour will be the basement slab for the building and the other will be the roof slab. This work will begin at 7 a.m., but because of the scale of this work, it will extend past normal work hours, concluding no later than 10:30 p.m. While we try hard to avoid working in the evening, this cement pouring cannot be interrupted, but rather has to be accomplished in a single day because of the nature of the material. We anticipate that there will be three more pours of this magnitude, probably occurring over the course of the next three weeks, and we will, as usual, provide advance notice.

May 7, 2008

May 8: A 15-foot broken concrete section of the sidewalk on Green Street in front of the Mendenhall Center for the Performing Arts will be removed and temporarily repaired with asphalt.

May 12: Curb and sidewalk installation will begin on Belmont and Ahwaga avenues. This work is expected to be completed by May 30.

April 30, 2008

May 5–8: Belmont and Ahwaga avenues will be paved. Final grading and rolling of gravel base will occur Monday, May 5, through Wednesday, May 7, and the roads will be paved on Thursday, May 8. This schedule is dependent upon no precipitation and will be extended as necessary in the event of rain. When the roads are finished, curbs and sidewalks will be installed. The schedule for their installation will be included in a future update.

April 29, 2008

May 1: There will be a shutdown of water utilities by the City of Northampton for the installation and tie-in of a fire hydrant on Belmont Avenue. The water shutdown will affect residents of 21 Belmont Avenue and Smith College faculty and staff at 27 and 30 Belmont Avenue. This work will be completed within one working day, between the hours of 8 a.m.–2 p.m.

May 6: A pump truck will be located on Arnold Avenue to pour concrete into the south section of the construction site. This work is expected to occur from 8:00 a.m. –1 p.m. and replaces the previously scheduled pour on May 1. Residents of 16 Arnold Avenue, who are affected by this work, are provided with parking passes in the Smith College parking garage.

April 23, 2008

April 24 and 25: A portion of the Green Street sidewalk across from the construction site will be closed to extend underground utilities. This work will begin at 7 a.m. on Thursday, April 24, and conclude by 3 p.m. on Friday, April 25.

April 25 and May 1: A pump truck will be located on Arnold Avenue to pour concrete into the south section of the construction site. This work is expected to occur from 8 a.m.-1 p.m. on both days. Residents of 16 Arnold Avenue, who are affected by this work, are provided with parking passes in the Smith College parking garage.

March 28, 2008

April 1: A pump truck will be located on Arnold Avenue to pour concrete into the south section of the construction site. This work is expected to occur from 8 a.m.-1 p.m. Residents of 16 Arnold Avenue, who are affected by this work, are provided with parking passes in the Smith College parking garage.

April 7, 8 and 9: Utilities will be installed in Green Street from the inner campus to the Ford Hall construction site. The installation will require Green Street to be closed to through traffic from the west side of the Dickinson Parking lot to the traffic circle in front of Sage Hall from 7 a.m.-5 p.m. each day. There will be vehicle access to Green Street businesses and to the Dickinson parking lot, and police officers will be present during the work hours to detour any through traffic.

March 18, 2008

March 24: In conjunction with the construction of Ford Hall, there will be road work on Belmont Avenue up to and along Ahwaga Avenue to replace utilities in those streets and to repave those work areas. This work will begin on Monday, March 24, and is expected to be completed by Friday, May 30. The days and hours of operation are Monday through Friday, 7 a.m.-5 p.m. The work areas will be re-opened at the end of each work day to allow for resident traffic.

While this road work is occurring, there will be no on-street parking on Belmont Avenue. Lower Belmont Avenue will be made a two-way street, with a police officer present to detour through traffic.

Residents of 21 Belmont Avenue and Ahwaga Avenue will be provided with Smith College temporary parking passes for campus parking lots/parking garage for those weeks when they will have limited or no vehicular access to their homes.

February 5, 2008

February 7: A pump truck will be located on Arnold Avenue to pour concrete into the south section of the construction site. This work is expected to occur from 8:00 a.m.-12:00 noon. Residents of 16 Arnold Avenue, who are affected by this work, are provided with parking passes in the Smith College parking garage.

January 30, 2008

Current: Due to weather-related delays, Ford Hall construction activity will occur on most Saturdays for the foreseeable future to maintain the project schedule. Work hours will be 8 a.m.-3:30 p.m. The type of construction occurring continues to be concrete pouring for the building’s structure.

January 3, 2008

January 4: A pump truck will be located on Arnold Avenue to pour concrete into the south section of the construction site. This work is expected to occur from 8:00 a.m.-3:30 p.m. Residents of 16 Arnold Avenue, who are affected by this work, are provided with parking passes in the Smith College parking garage.

Construction Updates

2008 Updates

2007 Updates

Contact Information

Project Background

News & Events

Webcam

Letters to the
Community

DirectoryCalendarCampus MapVirtual TourContact UsSite A-Z